Industrial and logistics construction in Germany: owner's representation, project management and site supervision

For companies that have to build in Germany without an in-house construction department. Our civil engineers represent you towards designers, general contractor and authorities, control schedule, cost and change orders and check execution until the building goes into operation.

Discuss my project +49 178 604 1571
In short

Schneider Theißing supports industrial and commercial construction on the owner side: production and manufacturing buildings, steel and precast halls, logistics and warehouse buildings, workshops and business parks, and lab and pharma buildings in the construction and coordination role. We provide owner's representation, project management under AHO Heft Nr. 9, general contractor procurement, site supervision, acceptance and progress reports in Frankfurt Rhine-Main, on the Bergstraße and in Rhine-Neckar, including expansions during operation. GMP qualification and cleanroom classification remain with the specialists responsible for them.

Starting point

Why industrial construction is more than a large hall

In industrial construction the production process defines the building, whether a manufacturing hall, workshop, assembly hall or plant extension: machine foundations, crane runways, media supply, ventilation, exhaust air and fire safety depend on the process. The contractor does not know the process, the equipment supplier does not know the building. In between stands the owner who has to bring both together, often during running production and with limited own capacity.

We take on this role for the company: we clarify requirements with production and management, check specifications and bids against the process requirements, supervise execution, coordinate the interface with the equipment suppliers and control schedule, cost and change orders up to acceptance.

Our civil engineers have supported hall construction, building construction, new build and refurbishment as well as logistics and data center projects. For data center campuses and hyperscale programmes see data center construction management.

Request

Discuss an industrial project

The request is non-binding. We reply personally on working days. Fees arise only with a written proposal that you accept. Your data is used solely to process your request.

Who we work for

Owners in industrial and commercial construction

Companies without a construction department

Management decides, we prepare: requirements programme, procurement model, bid comparison, decision papers and a monthly report on cost, schedule and risks. The project runs without being managed on the side from production.

International manufacturers

A new plant or extension in Germany, managed from headquarters abroad. We are the owner’s engineering presence on site, work in German with contractors and authorities and report in English.

Developers and investors

Logistics and commercial buildings are built to a fixed lease start. We supervise quality and schedule from the owner’s perspective, separate acceptance from tenant handover and review assets before acquisition or forward deal.

Lenders

For financing by construction progress we deliver progress reports with site inspection, completion per trade, reconciliation with the drawdown and the risks that drive the further course. See lender monitoring.

Building types

Which industrial and commercial buildings we support

01
Production and manufacturing

Machine foundations, crane runways, media routes, clear heights, delivery and expansion reserves. Requirements come from the process and are translated into loads, tolerances and interfaces before the award.

02
Steel and precast halls

Structure, erection sequence, connections, tolerances, corrosion protection, roof and wall cladding, for owners who order a hall on a turnkey basis.

03
Logistics and warehouses

Floor slab and flatness for racking, doors and docks, sprinklers, roof, external areas and the schedule up to lease start.

04
Lab and pharma buildings

Construction and coordination role: shell, fit-out, surfaces, tightness and interfaces with ventilation and process engineering. We keep the documentation so that the specialists can use it for qualification.

05
Workshops and business parks

Several users on one site: divisibility, fire compartments, tenant fit-out, access, parking and the line between base build and user requests.

06
Expansion during operation

Extension, additional storey or conversion while production continues: phasing plan with production and logistics, protection against dust, noise and vibration, traffic routing and releases per section.

Process

An industrial project from the owner’s perspective

Each phase contains a decision that is hard to change later. We prepare it and record who delivers what by when.

01

Requirements and site

Requirements programme from the process: areas, loads, media, clear height, crane, delivery, expansion reserve. With the designers we clarify the zoning plan and the permit route. If the installation is listed in Annex 1 of the 4th BImSchV, it needs a permit under the Federal Immission Control Act, which includes the building permit (section 13 BImSchG). That defines documents and schedule.

02

Design and permit

Fire safety concept under the industrial building guideline, requirements from the Workplace Ordinance (ArbStättV) and the technical rules for workplaces, energy concept, cost framework under DIN 276 and master schedule.

03

Procurement

Choice between general contractor (Generalunternehmer), turnkey contractor without own construction works (Generalübernehmer) and separate trade packages. Check the specification, make bids comparable, fix contract schedule, penalties and acceptance criteria such as floor flatness or roof tightness.

04

Execution

Site supervision with hold points: foundations, floor slab before concreting, structure before the roof, roof waterproofing before closing up. Change orders, cost and schedule monthly, interface list with the equipment suppliers.

05

Acceptance and start-up

Pre-inspection, formal acceptance, evidence for safety installations such as fire alarm, smoke extraction and sprinklers where state law requires inspections. Handover to operation and maintenance with complete documentation.

06

Warranty

Defect follow-up, list of deadlines and inspection before warranty periods expire, so that claims do not lapse.

Interfaces

Interfaces where industrial projects lose money

InterfaceTypical riskWhat we fix
Building and equipmentFoundations, openings, loads or connections do not match the machine deliveredInterface list with responsible party and date; supplier releases the foundation drawings before concreting
Floor slab and racking or vehiclesFlatness, joints or load capacity are not sufficient for racking and forklift operationLoad assumptions, flatness requirement and joint layout before award; measurement before acceptance
Structure and roofNo load reserve for photovoltaics, ventilation units or a later crane runwayLoad reserves in the requirements programme and in the structural design
Fire safety and servicesFire stopping, smoke extraction or sprinklers are not executed as the concept requiresCheck against the approved fire safety concept; hold points before closing up
Construction and running operationDust, vibration, closed traffic routes, risks for employeesPhasing plan, coordination of employers under section 8 ArbSchG, coordination under the Construction Site Ordinance
General contractor and userTenant or user requests become change orders during executionClear separation between base build and user fit-out in building description and schedule
German regulations

Rules that shape industrial buildings in Germany

We are not legal advisers and do not prepare fire safety concepts. We make sure these requirements are on the table early in the project and implemented on site.

  • Industrial building guideline (Industriebaurichtlinie): in Hesse the model guideline in the version of May 2019 applies as Annex HE 13 of the Hessian administrative regulation on technical building rules; in Baden-Württemberg the Industriebau-Richtlinie in the version of November 2025. It governs fire compartments, escape routes, smoke extraction and firefighting water.
  • Immission control: for installations under Annex 1 of the 4th BImSchV the authority decides within seven months in the formal procedure and within three months in the simplified procedure, counted from complete documents (section 10 (6a) BImSchG).
  • Workplaces: daylight and visual contact to the outside (Annex no. 3.4 ArbStättV), room temperature under ASR A3.5, traffic routes and loading ramps under Annex no. 1.8 and 1.10 ArbStättV.
  • State building codes: each federal state has its own building code (in Hesse the Hessische Bauordnung), which governs permits, special buildings and the inspection of safety installations.

Primary sources: BImSchG, 4th BImSchV, ArbSchG and ArbStättV on gesetze-im-internet.de; technical building rules of the federal states. German guides: Industriebaurichtlinie, Halle bauen, Industrieboden abnehmen.

Pharma, lab, brownfield

Pharma and lab buildings: our role on the construction side

Production conversions, brownfield extensions, equipment conversions, lab buildings, cleanroom areas and plant infrastructure share one feature: the construction site is not the owner’s main business, and operations continue. We provide site supervision, quality assurance and owner’s representation on the construction side and coordinate the interfaces with equipment, process design and qualification.

In a previous role, the managing directors supported the construction of a production plant for a pharmaceutical manufacturer on the Bergstraße in site supervision and quality assurance; the case study on our case studies page (German) is marked accordingly. We do not act as GMP or validation specialists. Qualification (DQ, IQ, OQ) and cleanroom classification remain with the specialists responsible. Our contribution is building quality, schedule and cost control and the documentation these specialists need. For English-speaking project teams see also QA/QC management.

FAQ

Frequently asked questions

The requirements come from the production process: higher loads, crane runways, media supply, exhaust air, fire safety under the industrial building guideline and often construction during operation. Errors in foundations or tolerances directly affect production and can hardly be corrected after start-up.
Yes, on the building side. We keep the interface list between building and equipment, check whether foundations, openings, loads and connections are delivered on time and correctly, and align equipment installation with the construction sequence. Responsibility for the equipment remains with the supplier.
With a construction phasing plan agreed with production, logistics and occupational safety: which areas are closed when, how traffic runs, which protective measures apply for dust, noise and vibration and who releases each construction section. Where employees of several employers work together they must coordinate under section 8 of the German Occupational Safety and Health Act; on construction sites the coordination under the Construction Site Ordinance (Baustellenverordnung) is added.
The Industriebaurichtlinie governs structural fire protection for industrial buildings: permitted size of fire compartments depending on safety category, fire resistance and number of storeys, as well as escape routes, smoke extraction and firefighting water. A fire safety engineer prepares the fire safety concept; we check whether execution matches the approved concept.
When the planned installation is listed in Annex 1 of the 4th BImSchV, for example certain surface treatment or metal processing installations or storage of certain substances. The immission control permit then includes other decisions such as the building permit (section 13 BImSchG). Whether this applies is clarified by designers and authority in each case; we take the permit route into account in the schedule.
Fees depend on scope, project size and construction period, with the HOAI and AHO Heft Nr. 9 as orientation. After a first call you receive a written proposal; a fee arises only once you accept it.

Build your industrial project with your own control function

Tell us the project stage, the contract model and the scope you need. You receive an engineering view and a written proposal.